The recent rain has meant little activity on the base. Assuming they're waiting on a few sunny days to commence on the slab but it's been almost 3 weeks since site start and we're getting a little impatient. Here's a photo of our muddy lot.
Noticed today that there has at least been some prep work with pipes and crushed rock.
Friday, June 18, 2010
Thursday, June 10, 2010
Meter Box and Recycled Water
Not a great deal has been happening given the recent rain. Though if this keeps up, we may just get that lap pool. It was good however to see our building permit and Metricon boards up as well as the meter box and what appears to be the recycled water tap (purple one in pic below). Not sure why it's positioned where it is, right in the middle up front of the land, and wondering if it will be relocated after construction.
Sunday, June 6, 2010
First Works